UC Santa Barbara is in an unprecedented era of construction and campus renewal. We understand the impact that this has on our campus and Facilities Management sincerely regrets any inconvenience to our visitors, faculty, staff and students. If you have any questions, please call or email the contact person referenced in the notice. Thank you for your patience.
Marc Fisher, Associate Vice Chancellor, Campus Design and Facilities
|
||||||||||||
| 36 – SAN CLEMENTE STUDENT HOUSING AND PARKING STRUCTURE | |||
| Affected Location(s) | |||
|
El Colegio Road Building #Other - See Additional Info |
|||
| Impact Type | Work Starts | Work Ends | Duration Type |
| Project under Construction |
3/1/2006 | 9/15/2008 | Ongoing |
| Contact Name | Contact Phone | Contact Dept. | Contact Email |
| Daniel Belding | (805) 451-0624 | Design & Construction Services | daniel.belding@dcs.ucsb.edu |
| Additional Information | |||
| Click here for additional details | |||
| 314 – Information Kiosk @ University Plaza Project | |||
| Affected Location(s) | |||
|
Lot 12 Building #Other - See Additional Info |
|||
| Impact Type | Work Starts | Work Ends | Duration Type |
| Traffic Interruption |
7/11/2008 | 8/22/2008 | Ongoing |
| Contact Name | Contact Phone | Contact Dept. | Contact Email |
| Deedee Ciancola | 805-451-5419 | Design & Construction Services | deedee.ciancola@pf.ucsb.edu |
| Additional Information | |||
| Click here for additional details | |||
| 316 – Concrete Removal @ Kirby Crossing and Steck Circle | |||
| Affected Location(s) | |||
|
Building #266 - CNSI (CAL NANOSCIENCE INST) |
|||
| Impact Type | Work Starts | Work Ends | Duration Type |
| Traffic Interruption |
7/21/2008 | 7/26/2008 | Ongoing |
| Contact Name | Contact Phone | Contact Dept. | Contact Email |
| Roger Monte | 805-451-3208 | Design & Construction Services | roger.monte@dcs.ucsb.edu |
| Additional Information | |||
| Click here for additional details | |||
| 317 – Fiber Cable Removal | |||
| Affected Location(s) | |||
|
Building #Other - See Additional Info |
|||
| Impact Type | Work Starts | Work Ends | Duration Type |
| Traffic Interruption Bike Path Interruption |
8/2/2008 | 8/10/2008 | Intermittent |
| Contact Name | Contact Phone | Contact Dept. | Contact Email |
| Carlyle Decker | 451-3867 | Design & Construction Services | carlyle.decker@dcs.ucsb.edu |
| Additional Information | |||